The Availability Manager node fixes allow you to deliberately fail (crash) a node or to adjust cluster quorum.
To perform a node fix, follow these steps:
The crash node fix is an operator-requested bugcheck from the driver. It takes place as soon as you click OK in the Crash Node page. After you perform this fix, the node cannot be restored to its previous state. After a crash, the node must be rebooted. |
When you select the Crash Node option, the Availability Manager displays the Crash Node page, shown in Figure 6-1.
Figure 6-1 Crash Node Page
Because the node cannot report a confirmation when a node crash fix is successful, the crash success message is displayed after the timeout period for the fix confirmation has expired. |
Recognizing a System Failure Forced by the Availability Manager
Because a user with suitable privileges can force a node to fail from the Data Analyzer by using the "Crash Node" fix, system managers have requested a method for recognizing these particular failure footprints so that they can distinguish them from other failures. These failures all have identical footprints: they are operator-induced system failures in kernel mode at IPL 8. The top of the kernel stack is similar the following display:
SP => Quadword system address
Quadword data
1BE0DEAD.00000000
00000000.00000000
Quadword data TRAP$CRASH
Quadword data SYS$RMDRIVER + offset
|
The Adjust Quorum fix forces the node to refigure the quorum value. This fix is the equivalent of the Interrupt Priority C (IPC) mechanism used at system consoles for the same purpose. The fix forces the adjustment for the entire cluster so that each node in the cluster will have the same new quorum value.
The Adjust Quorum fix is useful when the number of votes in a cluster falls below the quorum set for that cluster. This fix allows you to readjust the quorum so that it corresponds to the current number of votes in the cluster.
When you select the Adjust Quorum option, the Availability Manager displays the page shown in Figure 6-2.
Figure 6-2 Adjust Quorum Page
To perform a process fix, follow these steps:
Process General
Process Memory
Process Limits
Figure 6-3 Process General Options
Some of the fixes, such as Process Priority, require you to use a slider to change the default value. When you finish setting a new process priority, click Apply at the bottom of the page to apply that fix.
6.3.1 General Process Fixes
The following sections describe Availability Manager general process fixes.
6.3.1.1 Delete Process
In most cases, a Delete Process fix deletes a process. However, if a process is waiting for disk I/O or is in a resource wait state (RWAST), this fix might not delete the process. In this situation, it is useless to repeat the fix. Instead, depending on the resource the process is waiting for, a Process Limit fix might free the process. As a last resort, reboot the node to delete the process.
Deleting a system process could cause the system to hang or become unstable. |
When you select the Delete Process option, the Availability Manager displays the page shown in Figure 6-4.
Figure 6-4 Delete Process Page
After reading the explanation, click Apply at the
bottom of the page to apply the fix. A message displayed on the page
indicates that the fix has been successful.
6.3.1.2 Exit Image
Exiting an image on a node can stop an application that a user requires. Check the Single Process page first to determine which image is running on the node.
Exiting an image on a system process could cause the system to hang or become unstable. |
When you select the Exit Image option, the Availability Manager displays the page shown in Figure 6-5.
Figure 6-5 Exit Image Page
After reading the explanation in the page, click Apply
at the bottom of the page to apply the fix. A message displayed on the
page indicates that the fix has been successful.
6.3.1.3 Suspend Process
Suspending a process that is consuming excess CPU time can improve perceived CPU performance on the node by freeing the CPU for other processes to use. (Conversely, resuming a process that was using excess CPU time while running might reduce perceived CPU performance on the node.)
Do not suspend system processes, especially JOB_CONTROL, because this might make your system unusable. (See the HP OpenVMS Programming Concepts Manual, Volume I for more information.) |
When you select the Suspend Process option, the Availability Manager displays the page shown in Figure 6-6.
Figure 6-6 Suspend Process Page
After reading the explanation, click Apply at the
bottom of the page to apply the fix. A message displayed on the page
indicates that the fix has been successful.
6.3.1.4 Resume Process
Resuming a process that was using excess CPU time while running might reduce perceived CPU performance on the node. (Conversely, suspending a process that is consuming excess CPU time can improve perceived CPU performance by freeing the CPU for other processes to use.)
When you select the Resume Process option, the Availability Manager displays the page shown in Figure 6-7.
Figure 6-7 Resume Process Page
After reading the explanation, click Apply at the
bottom of the page to apply the fix. A message displayed on the page
indicates that the fix has been successful.
6.3.1.5 Process Priority
If the priority of a compute-bound process is too high, the process can consume all the CPU cycles on the node, affecting performance dramatically. On the other hand, if the priority of a process is too low, the process might not obtain enough CPU cycles to do its job, also affecting performance.
When you select the Process Priority option, the Availability Manager displays the page shown in Figure 6-8.
Figure 6-8 Process Priority Page
To change the base priority for a process, drag the slider on the scale to the number you want. The current priority number is displayed in a small box above the slider. You can also click the line above or below the slider to adjust the number by 1.
When you are satisfied with the new base priority, click
Apply at the bottom of the page to apply the fix. A
message displayed on the page indicates that the fix has been
successful.
6.3.2 Process Memory Fixes
The following sections describe the Availability Manager fixes you can use to correct process memory problems:
This fix purges the working set to a minimal size. You can use this fix to reclaim a process's pages that are not in active use. If the process is in a wait state, the working set remains at a minimal size, and the purged pages become available for other uses. If the process becomes active, pages the process needs are page-faulted back into memory, and the unneeded pages are available for other uses.
Be careful not to repeat this fix too often: a process that continually reclaims needed pages can cause excessive page faulting, which can affect system performance.
When you select the Purge Working Set option, the Availability Manager displays the page shown in Figure 6-9.
Figure 6-9 Purge Working Set Page
After reading the explanation on the page, click Apply
at the bottom of the page to apply the fix. A message displayed on the
page indicates that the fix has been successful.
6.3.2.2 Adjust Working Set
Adjusting the working set of a process might prove to be useful in situations similar to the following ones:
If the automatic working set adjustment is enabled for the system, a fix to adjust the working set size disables the automatic adjustment for the process. For more information, see OpenVMS online help for SET WORKING_SET/ADJUST, which includes /NOADJUST. |
When you select the Adjust Working Set fix, the Availability Manager displays the page shown in Figure 6-10.
Figure 6-10 Adjust Working Set Page
To perform this fix, use the slider to adjust the working set to the limit you want. You can also click the line above or below the slider to adjust the number by 1.
When you are satisfied with the new working set limit, click
Apply at the bottom of the page to apply the fix. A
message displayed on the page indicates that the fix has been
successful.
6.3.3 Process Limits Fixes
If a process is waiting for a resource, you can use a Process Limits fix to increase the resource limit so that the process can continue. The increased limit is in effect only for the life of the process, however; any new process is assigned the quota that was set in the UAF.
When you click the Process Limits tab, you can select any of the following options:
Direct I/O
Buffered I/O
AST
Open File
Lock
Timer
Subprocess
I/O Byte
Pagefile Quota
These fix options are described in the following sections.
6.3.3.1 Direct I/O Count Limit
You can use this fix to adjust the direct I/O count limit of a process. When you select the Direct I/O option, the Availability Manager displays the page shown in Figure 6-11.
Figure 6-11 Direct I/O Count Limit Page
To perform this fix, use the slider to adjust the direct I/O count to the limit you want. You can also click the line above or below the slider to adjust the number by 1.
When you are satisfied with the new direct I/O count limit, click Apply at the bottom of the page to apply the fix. A message displayed on the page indicates that the fix has been successful.
6.3.3.2 Buffered I/O Count Limit
You can use this fix to adjust the buffered I/O count limit of a
process. When you select the Buffered I/O option, the Availability Manager
displays the page shown in Figure 6-12.
Figure 6-12 Buffered I/O Count Limit Page
To perform this fix, use the slider to adjust the buffered I/O count to the limit you want. You can also click the line above or below the slider to adjust the number by 1.
When you are satisfied with the new buffered I/O count limit, click Apply at the bottom of the page to apply the fix. A message displayed on the page indicates that the fix has been successful.
6.3.3.3 AST Queue Limit
You can use this fix to adjust the AST queue limit of a process. When
you select the AST option, the Availability Manager displays the page shown in
Figure 6-13.
Figure 6-13 AST Queue Limit Page
To perform this fix, use the slider to adjust the AST queue limit to the number you want. You can also click the line above or below the slider to adjust the number by 1.
When you are satisfied with the new AST queue limit, click Apply at the bottom of the page to apply the fix. A message displayed on the page indicates that the fix has been successful.
6.3.3.4 Open File Limit
You can use this fix to adjust the open file limit of a process. When
you select the Open File option, the Availability Manager displays the page
shown in Figure 6-14.
Figure 6-14 Open File Limit Page
To perform this fix, use the slider to adjust the open file limit to the number you want. You can also click the line above or below the slider to adjust the number by 1.
When you are satisfied with the new open file limit, click Apply at the bottom of the page to apply the fix. A message displayed on the page indicates that the fix has been successful.
6.3.3.5 Lock Queue Limit
You can use this fix to adjust the lock queue limit of a process. When
you select the Lock option, the Availability Manager displays the page shown
in Figure 6-15.
Figure 6-15 Lock Queue Limit Page
To perform this fix, use the slider to adjust the lock queue limit to the number you want. You can also click the line above or below the slider to adjust the number by 1.
When you are satisfied with the new lock queue limit, click Apply at the bottom of the page to apply the fix. A message displayed on the page indicates that the fix has been successful.
6.3.3.6 Timer Queue Entry Limit
You can use this fix to adjust the timer queue entry limit of a
process. When you select the Timer option, the Availability Manager displays
the page shown in Figure 6-16.
Figure 6-16 Timer Queue Entry Limit Page
To perform this fix, use the slider to adjust the timer queue entry limit to the number you want. You can also click the line above or below the slider to adjust the number by 1.
When you are satisfied with the new timer queue entry limit, click Apply at the bottom of the page to apply the fix. A message displayed on the page indicates that the fix has been successful.
6.3.3.7 Subprocess Creation Limit
You can use this fix to adjust the creation limit of the subprocess of
a process. When you select the Subprocess option, the Availability Manager
displays the page shown in Figure 6-17.
Figure 6-17 Subprocess Creation Limit Page
To perform this fix, use the slider to adjust the subprocess creation limit of a process to the number you want. You can also click the line above or below the slider to adjust the number by 1.
When you are satisfied with the new subprocess creation limit, click Apply at the bottom of the page to apply the fix. A message displayed on the page indicates that the fix has been successful.
6.3.3.8 I/O Byte
You can use this fix to adjust the I/O byte limit of a process. When
you select the I/O Byte option, the Availability Manager displays the page
shown in Figure 6-18.
Figure 6-18 I/O Byte Page
To perform this fix, use the slider to adjust the I/O byte limit to the number you want. You can also click the line above or below the slider to adjust the number by 1.
When you are satisfied with the new I/O byte limit, click Apply at the bottom of the page to apply the fix. A message displayed on the page indicates that the fix has been successful.
6.3.3.9 Pagefile Quota
You can use this fix to adjust the pagefile quota limit of a process.
This quota is share among all the processes in a job. When you select
the Pagefile Quota option, the Availability Manager displays the page shown in
Figure 6-19.
Figure 6-19 Pagefile Quota Page
To perform this fix, use the slider to adjust the pagefile quota limit to the number you want. You can also click above or below the slider to adjust the fix value by 1.
When you are satisfied with the new pagefile quota limit, click
Apply at the bottom of the page to apply the fix. A
message displayed on the page indicates that the fix has been
successful.
6.4 Performing Cluster Interconnect Fixes
Cluster interconnect fixes have been added to the Availability Manager beginning in Version 2.0. The following are categories of cluster interconnect fixes:
The following sections describe these types of fixes and tell how to
access them and how to perform them. The descriptions also indicate
whether or not the fix is currently available.
6.4.1 Port Adjust Priority Fix
To access the Port Adjust Priority fix, right-click a data item in the local port data display line (see Figure 4-3). The Availability Manager displays a popup menu with the Port Fix option.
This page (Figure 6-20) allows you to change the cost associated with this port, which, in turn, affects the routing of cluster traffic.
Figure 6-20 Port Adjust Priority Page
To access the Circuit Adjust Priority fix, right-click a data item in the local port data display line (see Figure 4-4). The Availability Manager displays a popup menu with the Circuit Fix option.
This page (Figure 6-21) allows you to change the cost associated with this circuit, which, in turn, affects the routing of cluster traffic.
Figure 6-21 Circuit Adjust Priority Page
To access LAN virtual circuit summary fixes, right-click a data item in the LAN Virtual Circuit Summary category (see Figure 4-6). The Availability Manager displays a popup menu with the following options:
When you select VC LAN Fix..., the Availability Manager displays the first of several fix pages, the Maximum Transmit Window Size. By clicking Maximum Transmit Window Size, you can display a list of all the LAN VC summary fixes:
These fixes are described in the following sections.
6.4.3.1 LAN VC Maximum Transmit Window Size Fix
This page (Figure 6-22) allows you to adjust the maximum transmit
window size for the virtual circuit.
As of OpenVMS Version 7.3-1, this fix is not recognized by PEDRIVER. However, the fix might become available in a future OpenVMS or remedial release. |
Figure 6-22 LAN VC Maximum Transmit Window Size Page
6.4.3.2 LAN VC Maximum Receive Window Size Fix
This page, (Figure 6-23) allows you to adjust the maximum receive
window size for the virtual circuit.
As of OpenVMS Version 7.3-1, this fix is not recognized by PEDRIVER. However, the fix might become available in a future OpenVMS or remedial release. |
Figure 6-23 LAN VC Maximum Receive Window Size Page